HP3000-L Archives

September 1998, Week 2

HP3000-L@RAVEN.UTC.EDU

Options: Use Monospaced Font
Show Text Part by Default
Show All Mail Headers

Message: [<< First] [< Prev] [Next >] [Last >>]
Topic: [<< First] [< Prev] [Next >] [Last >>]
Author: [<< First] [< Prev] [Next >] [Last >>]

Print Reply
Subject:
From:
"Davis, Larry" <[log in to unmask]>
Reply To:
Davis, Larry
Date:
Tue, 8 Sep 1998 09:54:32 -0400
Content-Type:
text/plain
Parts/Attachments:
text/plain (20 lines)
Subject:        Maestro Calendars


 I am currently working to create calendars for schedules that will be
defined using a MPE box.  These schedules will need unusual calendar
days, such as: the 4th to last work day of the month, the 22nd of the
month, the 1st Tuesday of the month, the weekend closest to the 15th for
months March, June, Sept, and Dec. This goes on and on with about 40
schedules that needs these type of scheduling days.  The last place I
worked used more conventional scheduling days with Maestro like
workdays, everyday or weekly on a certain day etc.  My question is with
the different schedules having such varied needs, should I set up a
calendar for each schedule or is there an easier way?

Thanks,

Larry Davis
Trigon Blue Cross Blue Shield
Richmond, Virginia