HP3000-L Archives

July 2000, Week 4

HP3000-L@RAVEN.UTC.EDU

Options: Use Monospaced Font
Show Text Part by Default
Show All Mail Headers

Message: [<< First] [< Prev] [Next >] [Last >>]
Topic: [<< First] [< Prev] [Next >] [Last >>]
Author: [<< First] [< Prev] [Next >] [Last >>]

Print Reply
Subject:
From:
Eben Yong <[log in to unmask]>
Reply To:
Eben Yong <[log in to unmask]>
Date:
Fri, 28 Jul 2000 08:20:59 -0700
Content-Type:
text/plain
Parts/Attachments:
text/plain (43 lines)
MPE6.0 has this new feature?  Sounds good.  Currently, I am on MPE5.5PP7 and
awaiting MPE6.5PP1...

-----Original Message-----
From: Michael Berkowitz [mailto:[log in to unmask]]
Sent: Friday, July 28, 2000 7:54 AM
To: 'Eben Yong'; [log in to unmask]
Subject: RE: MPEX question


Eben Yong writes:

-----Original Message-----
From: Eben Yong [mailto:[log in to unmask]]
Sent: Thursday, July 27, 2000 5:45 PM
To: [log in to unmask]
Subject: MPEX question


Hello,

I am putting together a rudimentary MPEX script that does basic job
scheduling.  The objective is to allow jobs to run sequentially.  The script
uses HIPRI.CMD.VECSL to facilitate job execution but it is bombing at the
ALTJOB statement in the HIPRI command file.  If you'll scroll down to the
$stdlist, you will see that the statement is not failing due to syntax, but
due to an FSERR.  I am confused as to why the HIPRI command file fails in
this BATCH job.  Here's the controlling script, the HIPRI.CMD.VECSL source
code and the $stdlist:

Thanks for any assistance!

Eben Yong
MIS Manager
Health Plan of San Mateo
------------------------------------------------------------------
Why go to all that much trouble.  If you're on 6.0 use the multiple
jobqueues to single thread the jobs that need it, and multiple thread
others.  Much easier than a do it your self operation.

Mike Berkowitz