HP3000-L Archives

January 2001, Week 2

HP3000-L@RAVEN.UTC.EDU

Options: Use Monospaced Font
Show Text Part by Default
Show All Mail Headers

Message: [<< First] [< Prev] [Next >] [Last >>]
Topic: [<< First] [< Prev] [Next >] [Last >>]
Author: [<< First] [< Prev] [Next >] [Last >>]

Print Reply
Subject:
From:
Doug Werth <[log in to unmask]>
Reply To:
Doug Werth <[log in to unmask]>
Date:
Fri, 12 Jan 2001 21:02:57 -0500
Content-Type:
text/plain
Parts/Attachments:
text/plain (34 lines)
Ken Sletten writes:

>
> But without the capability to execute a programmatic
> <CTRL>-A  -  SHUTDOWN, apparently will always have to
> resync mirrors when come back up after unplanned power
> outage.....   I've got to think (hope) that an enhancement to
> allow launch of a SHUTDOWN sequence in a job would not
> be a huge project....
>
> Without a programmatic SHUTDOWN feature, I agree that
> at some point the resync time becomes hard to swallow.....
>

<speculation>

I think that if you VSCLOSE the mirrored volume set prior to the =SHUTDOWN
then it may not matter whether or not the system reaches SHUT 6 because the
volume set is not mounted at the time of shutdown. If my speculation is true
the VSCLOSE will perform all synchronization steps and flag the volume set
as 'good' just as the shutdown process would.

I don't currently have a mirrored set to test with but when I get a chance I
will test it and report my results. In the meantime, if someone has the
opportunity to test this on a non-critical, non-production system and report
back sooner of course I think we would all be interested.

</speculation>